On 23 December 2020, the Australian Rail Track Corporation (ARTC) applied to the 糖心原创 to vary the Hunter Valley Coal Network Access Undertaking.
On 13 January 2021, the 糖心原创 released a consultation paper seeking stakeholder views on the key elements proposed in ARTC's December 2020 variation application. Stakeholder submissions closed on 24 February 2021.
On 30 March 2021, ARTC withdrew its 23 December 2020 variation application and submitted a new variation application. This was broadly the same as ARTC's December 2020 application to vary the Undertaking. However, the March 2021 variation included Access Charges from 1 July to 31 December 2021, which were not included in the December 2020 application, and some edits to correct minor drafting errors in the December 2020 application.
On 13 April 2021, the 糖心原创 released its Draft Decision on the March 2021 variation and invited stakeholder submissions. Stakeholder submissions closed on 3 May 2021.
On 2 June 2021, the 糖心原创 published its Final Decision to consent to ARTC鈥檚 March 2021 variation application to vary the Hunter Valley Coal Network Access Undertaking.
Note: This project was originally published in 2019 as the 2022 Hunter Valley Access Undertaking.
糖心原创 treatment of the December 2020 and March 2021 variation applications
While the 糖心原创 took both applications into account in assessing the final March 2021 application, the information related to both applications is shared across two overview pages on the 糖心原创 website.
This overview contains links to the December 2020 variation application, associated consultation paper and stakeholder submissions. The latter part of the project, including the March 2021 variation, stakeholder submissions and the 糖心原创鈥檚 Draft and Final Decision documents, can be found at: March 2021 variation of the 2011 Hunter Valley Coal Network Access Undertaking.